The opportunity cost amounts to $532,000. This represents the cost of the most preferable alternative that was not selected. In this case, rejecting the investment project meant foregoing the potential return of $532,000.
Answer:
IRR = 14.96%
The project should be rejected, because the calculated internal rate of return falls short of the required return (14.96% < 16%).
Explanation:
The internal rate of return (IRR) is an essential calculation in capital budgeting for assessing potential investment profitability. The IRR rule guides whether to pursue a project or investment, stipulating that if the IRR exceeds the minimum required return, the project should be accepted. Conversely, if it’s lower than the cost of capital or the requisite return, the project should be turned down.
The formula used is as follows:
$0 = (initial investment x -1) + CF1 / (1 + IRR) ^ 1 + CF2 / (1 + IRR) ^ 2 +... + CFX / (1 + IRR) ^ X
Initial Investment = Total initial investment costs year x-1
CFx = Cash Flow during period X
IRR = Internal rate of return
Due to the nature of the IRR formula, it cannot be computed analytically; it must be derived through trial and error or via specialized software for IRR calculation.
In this instance:
IRR = -27200 + 11200 / (1 + IRR) ^ 1 + 14200 / (1 + IRR) ^ 2 + 10200 / (1 + IRR) ^ 3
IRR = 14.96%
The company should not proceed with the investment, as the calculated IRR is less than what is required (14.96% < 16%).
To make both Site options equally appealing, Mark's utility for a $50,000 profit ought to be set at 0.78. Explanation: For an individual to be indifferent between two site choices, the utility levels for Site 1 and Site 2 need to align. The weighted utility for Site 2, based on good demand, is calculated by averaging, resulting in 0.5. For Site 1, the balance between Ux and a lower utility must sum to 0.5. Calculating Ux gives us a resultant of 0.78.
Response: appropriate hygiene practices
Justification:
Answer:
The correct answers are b. As batch size grows, lead time shrinks and d. The Product Owner influences batch size, while the Development Team determines utilization.
Explanation:
Generally, when the batch size increases, lead time also rises, as smaller batches can be processed quicker compared to larger ones, which take extra time. Additionally, the product owner influences the batch size based on market demand, and the development team conducts utilization tests to inform their decisions that affect how resources are utilized.